MBTA Red Line Trough/Winter Resiliency

Project Details

Project Value: $16M

For this project, Barletta replaced over 2,300 track feet of full depth ballasted transit construction, installed 9 miles of new third rail and insulators over 8 weekend diversions, replaced over 500 ties, replaced third rail feeder cables and conducted operational testing of feeder cables, installed 22,000 feet of new raceway and hand holes for new third rail heater elements, and completed electrical and signal upgrades.