Estimated Project Value: $13M
The scope of work for this project consisted of Wayfinding and Station Improvements, including demolishing/replacing/retrofitting all station lighting throughout the public areas, and relocating existing cameras; demolition and replacement of all existing wayfinding signage; providing compliant Braille signage at the two historical headhouses and throughout the public areas of the station platforms; providing illuminated exit signage throughout the station; repairing floor finishes, benches, and 24 staircases; reopening the Temple Place stairs on Tremont Street, station brightening (cleaning and painting) and cleaning of artwork. The work was phased to minimize disruptions to customers and subway operations, and the majority of the work was performed between 9 pm and 5 am.