MBTA Science Park / West End Station (A29CN04)

 
Location: Boston, Massachusetts
Contract Value: $11,533,188
Project Dates: February 2010 - March 2012

This project consisted of improvements to the Science Park / West End MBTA Green Line Station, including the rehabilitation, widening, reconstruction of parapets, decks, walls, stairways, arches and railings of the historic Lechmere Viaduct, and the rehabilitation / replacement of stairs, railings and lighting at Craigie Bridge.

Barletta proposed a resequencing plan to mitigate the minimum 12 month delay being caused by an adjacent contract.  The station was closed for 6 months, reopening in November 2011.  Working closely with the MBTA and MBTA Operations, Barletta completed 18 months of work in 6 months, driving the entire project to completion 2 months earlier than originally projected.